Sage 50 CIS module help please!
Posted: 14 Jun 2019, 11:27
Hello,
I’ve recently started using the Sage CIS module to post subcontractor invoices including CIS deductions.
Some invoices have further deductions for things such as training costs.
I’m having trouble posting and paying these particular invoices including the further deductions.
I can’t seem to be able to post a subcontractor payment without it deducting the training costs (posted as a separate credit note) before it’s deducting the CIS from the labour amount.
For example:
Labour £800
- CIS @ 20% £160
Total: £640
- £50 training costs
Total payable to sub-con: £590.
How can I do it this way in sage please? All its letting me do is allocate the credit first so it’s taking the £50 off the £800 which is then making the CIS deduction incorrect!
Any help would be greatly appreciated, i’m currently at a loss what to do!!
I’ve recently started using the Sage CIS module to post subcontractor invoices including CIS deductions.
Some invoices have further deductions for things such as training costs.
I’m having trouble posting and paying these particular invoices including the further deductions.
I can’t seem to be able to post a subcontractor payment without it deducting the training costs (posted as a separate credit note) before it’s deducting the CIS from the labour amount.
For example:
Labour £800
- CIS @ 20% £160
Total: £640
- £50 training costs
Total payable to sub-con: £590.
How can I do it this way in sage please? All its letting me do is allocate the credit first so it’s taking the £50 off the £800 which is then making the CIS deduction incorrect!