POP due in dates
Posted: 09 Mar 2015, 16:03
by cliffox
Another question that has popped up is how Sage handles POP due in dates. We have multi-line orders and often the supplier will confirm different dates for each item but at present, we can only have a due date for the whole order. Is there any way of having due date by line item, other than exporting the PO into Excel and doing it there?
POP due in dates
Posted: 09 Mar 2015, 17:08
by brucedenney
There are 2 sets of due dates, one on the order and on each line item.
If you set the due dates on the line items you should be fine.
You may need to alter some reporting to use the date off the items rather than the orders.
Bruce
P.S. Could you please start new topics for new questions
Re: POP due in dates
Posted: 09 Mar 2015, 17:59
by cliffox
Many thanks Bruce!
..and apologies ref the new topic!
Didn't see a due date option per line item but will look again tomorrow, thanks again!